Street · 205 of 8,565 by permit count
Building permits on Bond St
The City of Toronto has 630 building permits on record for Bond St, going back to 1991. Declared construction value totals $434.5M. The most recent permit was issued Sep 9, 2026 at 30 Bond St.
- Permits on record
- 6301991–2026
- Declared construction value
- $434.5Mas filed, not adjusted
- Homes created
- 0dwelling units
- Homes removed
- 0net +0
Permits issued per year
20002026 (part year)
Most common work
Structures worked on
Most recent permits
| Issued | Work | What was filed | Value | Status |
|---|---|---|---|---|
| Sep 9, 2026 | Sprinklers | Revision 04: revised drawings. REV 02: Revision to sprinkler system.Proposal for a new Fire Sprinkler System in an existing hospital - Shuter Tower (levels B3 to L3) and in the Cardinal Carter Wing renovation area L1 | — | Open |
| Sep 2, 2026 | Inside and Outside Drains | Drain - Proposal for interior alterations and an 8 storey addition to the existing building to serve as the new Student Health and Wellness Centre - O'Keefe House, Toronto Metropolitan UniversitySee also 22 156133 ZAP, 22 237820 SA and 23 131626 MV. | $900K | Open |
| Jul 21, 2026 | Building Permit Related(PS) | Plumbing - Convert Rm 4 072B, Donnelly Wing of St. Michael's Hospital into an accessible washroom to support on¿call staff. | — | Open |
| Jul 21, 2026 | Building Permit Related(MS) | HVAC - Convert Rm 4 072B, Donnelly Wing of St. Michael's Hospital into an accessible washroom to support on¿call staff. | — | Open |
| Jul 16, 2026 | Partial Permit - Shoring | Conditional Permit - Part Permit - Proposed construction of a new 21 storey student residence including 1 level of basement (Assembly School) Toronto Metropolitan University. | — | Open |
| Jul 15, 2026 | Interior Alterations | Rev 05 - Interior updates to peri-operative and Anesthesia classroom. Extended DW5C fit up.REVISION 4 - minor alterations at DW5C levelProposal for interior alterations to on 5th floor - Donnelly Wing Central and North Peri Operative. areas in existing hospital. | — | Closed |
| Jul 15, 2026 | Building Permit Related(PS) | Rev 05 - Interior updates to peri-operative and Anesthesia classroom. Extended DW5C fit up.REVISION 4 - minor alterations at DW5C levelPlumbing - Proposal for interior alterations to on 5th floor - Donnelly Wing Central and North Peri Operative. areas in existing hospital. | — | Open |
| Jul 15, 2026 | Building Permit Related(MS) | Rev 05 - Interior updates to peri-operative and Anesthesia classroom. Extended DW5C fit up.REVISION 4 - minor alterations at DW5C levelHVAC - Proposal for interior alterations to on 5th floor - Donnelly Wing Central and North Peri Operative. areas in existing hospital. | — | Open |
| Jun 25, 2026 | Interior Alterations | Convert Rm 4 072B, Donnelly Wing of St. Michael's Hospital into an accessible washroom to support on call staff. | $100K | Open |
| May 19, 2026 | Sprinklers | Proposal to provide F-K-5-1-12 Clean Agent System to Serve Hub Rooms and Electrical Rooms, and to provide fire alarm devices in 10th floor Existing Data Centre 10-183 and UPS room 10-184 and connect to existing building fire alarm control network. | $300K | Open |
| May 8, 2026 | Sign Building Permit Related | A sign permit to erect and display 1 overhanging structure sign + 4 wall signs, all displaying static copy.**THE SLAIGHT FAMILY EMERGENCY DEPARTMENT** | — | Open |
| May 6, 2026 | Addition(s) | Rev 02: see cover letterRev 01: see cover letterProposal to construct a 2-storey addition to existing hospital. Scope of work includes demolishing existing 6 storey Shuter Wing and constructing new Shuter Wing. See STE 16-148963. | — | Open |
| May 4, 2026 | Building Permit Related(MS) | Rev 03: see cover letterRev 02: see cover letterREV 01: as per Builidng Inspector Deficiency request, see cover letter for scope HVAC - Proposal to construct a 2-storey addition to existing hospital. Scope of work includes demolishing existing 6 storey Shuter Wing and constructing new Shuter Wing) S | — | Open |
| Apr 28, 2026 | Other(MS) | Proposal for installation of geothermal piping for a new 21-storey of student residence | $80K | Open |
| Apr 27, 2026 | Building Permit Related(PS) | Plumbing - Proposal for interior alterations and an 8 storey addition to the existing building to serve as the new Student Health and Wellness Centre - O'Keefe House, Toronto Metropolitan UniversitySee also 22 156133 ZAP, 22 237820 SA and 23 131626 MV. | — | Open |
| Apr 27, 2026 | Multiple Projects | Proposal for 8 storey addition to an existing 2 storey building that is to be partially demolished and altered to serve as the new Student Health and Wellness Centre - O'Keefe House, Toronto Metropolitan UniversitySee also 22 156133 ZAP, 22 237820 SA and 23 131626 MV. | $20.0M | Open |
| Apr 15, 2026 | Building Permit Related (DR) | Drain - Proposal for interior alterations and an 8 storey addition to the existing building to serve as the new Student Health and Wellness Centre - O'Keefe House, Toronto Metropolitan UniversitySee also 22 156133 ZAP, 22 237820 SA and 23 131626 MV. | — | Open |
| Apr 13, 2026 | Inside and Outside Drains | Drain - Proposed construction of a new 21 storey student residence including 1 level of basement (Assembly School) Toronto Metropolitan University. | — | Open |
| Apr 13, 2026 | Electromagnetic Locks | REVISION 3 - Revision to permit to remove the maglock from Door CN-L-B2AAdd 32 electromagnetic locks in Shuter Tower (levels B3 to L3) and in the Cardinal Carter Wing renovation area L1. Building permit: 16-260971 | — | Open |
| Apr 1, 2026 | Other(BA) | Spatial Seperation application for building to Toronto Metropolitan University's Student Wellbeing Center 9 Refer to 137 Bond St - Permit # 23-195157 BLD 00 BA). | $98K | Closed |
| Mar 20, 2026 | Building Permit Related(PS) | Rev 02: see cover letterRev 01: see cover letterPlumbing - Proposal to construct a 2-storey addition to existing hospital. Scope of work includes demolishing existing 6 storey Shuter Wing and constructing new Shuter Wing) See STE 16-148963. | — | Closed |
| Feb 24, 2026 | Interior Alterations | Proposed interior alteration on Level 15 to relocate NICU. Proposed work includes a new air handling unit (AHU) in the roof, complete with service stair and platform. | $18.0M | Open |
| Feb 19, 2026 | Building Permit Related(PS) | Plumbing - Proposed interior alteration on Level 15 to relocate NICU. Proposed work includes a new air handling unit (AHU) in the roof, complete with service stair and platform. | — | Open |
| Feb 19, 2026 | Building Permit Related(MS) | HVAC - Proposed interior alteration on Level 15 to relocate NICU. Proposed work includes a new air handling unit (AHU) in the roof, complete with service stair and platform. | — | Open |
| Feb 2, 2026 | Demolition | Demolition of existing 4 storey commercial building | — | Demolition |
| Jan 30, 2026 | Demolition | Demolition of existing 3 Storey commercial building | — | Demolition |
| Jan 30, 2026 | Demolition | Demolition of existing 3 Storey commercial building | — | Demolition |
| Jan 6, 2026 | Building Permit Related(PS) | Revision 03: Revision to PLB - Donnelly Wing Flr 2 - Interior RenovationsREV 01 - Revision to PLB- Description in attachedPlumbing - Proposed scope of work involves demolition of interior partition walls and ceilings, and redesign and resinstallation of interior layout on the second floor of St. Mic | — | Closed |
| Dec 31, 2025 | Building Permit Related(MS) | Revision 03: Revision to HVAC - Donnelly Wing Flr 2 - Interior RenovationsREV 01 - Revision to HVAC - Description in attachedHVAC - Proposed scope of work involves demolition of interior partition walls and ceilings, and redesign and reinstallation of interior layout on the second floor of St. Micha | — | Closed |
| Dec 19, 2025 | Partial Permit - Foundation | Part Permit - Proposed construction of a new 21 storey student residence including 1 level of basement (Assembly School) Toronto Metropolitan University. | — | Open |
| Dec 19, 2025 | Partial Permit - Structural Framing | Part Permit - Proposed construction of a new 21 storey student residence including 1 level of basement (Assembly School) Toronto Metropolitan University. | — | Open |
| Dec 10, 2025 | Other(BA) | Proposal for a temporary base for a tower crane. The date ofinstallation will be November 6th 2025 and the removal will be on March 15th 2027. | $80K | Closed |
| Nov 26, 2025 | Fire Alarm | Replacement of existing fire alarm system, including all controls, and field devices | $50K | Open |
| Nov 14, 2025 | Building Permit Related(MS) | HVAC - Proposal for interior alterations for Palliative Care unit refrece - level 4 Donnelly Wing | — | Open |
| Nov 14, 2025 | Building Permit Related(MS) | HVAC - Proposal to replace existing stage, (50.6 m2), front stage stairs and floors. | — | Open |
| Nov 14, 2025 | Multiple Projects | Proposal to replace existing stage, (50.6 m2), front stage stairs and floors. | $190K | Open |
| Nov 14, 2025 | Interior Alterations | Proposal for interior alterations for Palliative Care unit refresh - level 4 Donnelly Wing | $50K | Open |
| Nov 14, 2025 | Building Permit Related(PS) | Plumbing - Proposal for interior alterations for Palliative Care unit refrece - level 4 Donnelly Wing | — | Open |
| Oct 30, 2025 | Interior Alterations | Revision 02: Revision to main BLD - Description in attachedREV 01 - Revision to main BLD - Description in attachedProposed scope of work involves demolition of interior partition walls and ceilings, and redesign and resinstallation of interior layout on the second floor of St. Michael's Hospital, Do | — | Closed |
| Oct 23, 2025 | Interior Alterations | Proposal for interior alterations to upgrade MRI rooms 1 & 4, also level B2 Cardinal Carter Wing. | $1.3M | Open |
The 40 most recent of 630 permits on record. Figures come from the City’s active and cleared permit datasets, refreshed daily — what that covers, and what it misses.